Best Value - Weighted Scoring: Proposal Ranking

3suppliers-full.png

 

Technical (Qualitative) Score
for Supplier C
 Financial (Quantitative) Score
for Supplier C
  
87 77.78  
Combined Weighted
Qualitative Score
 Combined Weighted
Quantitative Score 
 Total Combined
Weighted Score 
65.25 +19.45 =84.70

In this example, note how Supplier C is ranked number one even though Supplier C did not have the lowest Financial Proposal

With Best Value, cost is often not the driving factor for awarding bids. It is important, but not to the point of overriding qualitative factors such as quality and effectiveness of goods/services, or supplier’s expertise, or commitment to sustainability.